The Municipal Airport Authority would
like to recap the completed and upcoming projects at
Hector International Airport for 2000 and 2001.
Approximately $4.6 million was spent on airport
improvement projects for the year.
Q
Remodeled passenger terminal restrooms -
The entrances were reconfigured to allow
easy, unobstructed access. New counter-tops, stall
dividers, hand dryers and fixtures were installed.
Cost was $130,000
Q
Replacement of
sewer and
water main for the south general aviation area -
The old system dating back to the 1950s was
replaced. Cost $360,000
Q
Completed a transient aircraft parking area
adjacent the new air museum - This ramp was
completed last week. It will allow visiting aircraft
to park near the new air museum, which is scheduled
to open next year. Cost $135,000
Q
Demolition/removal of the old control tower
located on the east terminal - The old
structure was removed from the old terminal building
because it was unusable and could not cost
effectively be maintained.
Cost $100,000
Q
Constructed a 208' x 120'
precast concrete
hangar in south general aviation area - The
two hangars will house aircraft and be leased by
both Valley Aviation and Fargo Jet Center. Valley
Aviation will use its portion to store the aircraft
for Flight Training Ltd. Fargo Jet Center is leasing
the hangar for the new Aero Manufacturing
Engineering program at North Dakota State
University. Cost $1,200,000 (This project is
funded by the insurance proceeds from the July 4,
1999 storm that damaged numerous buildings at the
airport.)
Q
Replaced and added additional sidewalks
adjacent the passenger terminal -
Additional sidewalks were installed to better
accommodate the increase in traffic. The sidewalk
from the terminal to the car rental lot was
replaced. Cost $5,485
Q
Acquired a Turbo-Way passenger lift device -
This device is now required by the Federal Aviation
Administration as part of the American with
Disabilities Act. The device will be used to assist
individuals to board turbo-prop aircraft safely.
Cost $24,859
Q
Updated the Airport Master Plan -
The airport master plan is required by the Federal
Aviation Administration (FAA) to be updated every
ten years. The master plan predicts the growth of
the airport for the next twenty years.
Cost
$195,409
Q
Constructed a fire training facility -
This facility was built for the ND Air National
Guard and was commissioned for training use in the
spring of 2000. The facility has a 50-foot mock-up
of an aircraft fuselage and allows the fire
personnel to train on fighting aircraft
fires/emergencies. Cost $850,000. (This project
was funded by the Air National Guard)
Q
Construction of vehicle perimeter roads -
The FAA required the airport to construct a
perimeter road system to more efficiently allow
airport vehicles access to the various areas of the
airport without crossing the runways. The first two
roads were constructed this year. The roads connect
the north general aviation area to the passenger
terminal ramp and also to the south general aviation
ramp. Cost $900,000
Q
Purchase snow removal equipment -
The MAA is purchasing two airport snowplow trucks
manufactured by Oshkosh. The units are an all-wheel
drive, all-wheel steer plow truck with a front
mounted 24’ batwing plow. These two units will be
the primary equipment to clear snow from the airport
surfaces. The MAA also purchased a 16-yard sand
truck. The truck will be a Sterling truck with a
Swenson sand-box with 500 gallon tanks for
prewetting capabilities. This equipment is replacing
equipment existing equipment.
Cost $685,000
NOTE: All
costs listed are estimates
Upcoming projects for 2001
include:
Q Install a
Flight Information Display System
Q Update
passenger terminal departure lounge and other public
area seating
Q Install business
centers in the passenger terminal
Q Improve safety
area for runway 08/26 extension
Q Extend runway
08/26 approximately 1,900 feet to the west
Q Install a new
taxiway from the end of runway 08/26 to the passenger
terminal ramp.
Q Continued
planning for the construction of a car rental facility